GOS was awarded to do ballast tank repairs on an LNG tanker in the forepeak tank whilst under voyage.
Vessel travelled from SEA to Middle East and South America while GOS crew onboard did the coating repairs in the forepeak tank.
This was in done in 2 phases and a second team continued the job on the vessel and the riding crew joined in Europe shipyard and departing the vessel after completion of the works in South America.
Steelpaint was used as a primer to attack the repairs locations after treatment with slurry blasting / power tooling (bristle blaster) using as surface preparation techniques.
Location: On voyage-worldwide
Duration: total of approx 120 days