GOS was requested to use hydro demolition on a newly under construction power plant due to some hardness issues with the newly used concrete. To be able to just remove concrete only and leave the reinforcement bars in place hydro demolition is the fastest way to go as GOS has proven quite a few times over and over again, saving construction companies a lot of time and rapid progress of their construction projects. Project was started during the COVID period and in despite the difficulties and delays we are proud to say we overcome all the difficulties and were able to mobilise with only slight delays and performed the job safely for all our employees and client. Machinery was mobilised from our Malaysian entity to Semaran and our crew came from various parts of Indonesia. It shows the flexibility and power of GOS to overcome difficulties and to stay focussed on the project and make things happen.